Contractors Working Directly for Homeowners – The Consumer Protection Act May Limit Your Ability to Charge More than your Estimate

August 2, 2023 Construction & Infrastructure Bulletin 4 minute read

In The Fifth Wall Corp. v. Tonelli[1], the Ontario Superior Court of Justice held that the Ontario Consumer Protection Act (“CPA”) applied to a residential construction contract entered into between a general contractor and a homeowner.

This ruling is significant because contractors contracting directly with homeowners may now be precluded from charging more than 10% over and above any estimate provided in the contract.

This is the first case dealing with this issue directly. This bulletin summarizes the Court’s decision and the key takeaways for builders and homeowners dealing with residential construction contracts.

Background

The Fifth Wall Corp. (“Fifth Wall”), a builder/general contractor (“builder”), was contracted to build a new residential house – their “dream home” – for the defendant homeowners (“homeowners”). The contract included a description of the scope of work for the home along with cost-coded line items, each with a specific dollar amount listed in a column titled “budget”.[2]

Work on the home proceeded between June 2016 and December 2018. Some changes and extras were performed during that time. The builder’s costs for certain items therefore exceeded the “budget” amounts listed in the contract. By October 2018, the builder asserted changes totalling over $400,000.[3] The homeowners alleged that they were not aware of and did not approve any changes, extras or cost increases that exceeded the budget amounts listed in the contract.[4]

Under the CPA, a supplier of goods or services is limited to charging only 10% more than an original estimate. A supplier of goods or services may charge beyond this 10% limit only if there is agreement by the consumer to amend the estimate.[5]

The homeowners therefore brought a motion for partial summary judgement seeking a declaration that the CPA applied to their residential construction contract (thereby limiting the builder to charging only 10% more than the original estimate for each item of work). If the CPA applied, the homeowners also sought an order requiring the builder to pay damages under the CPA for the amounts the homeowners had overpaid on the estimates provided by the builder.[6]

The Court Determines the CPA Can Apply to Residential Construction Contracts

In deciding whether to grant summary judgement, the Court first considered whether the CPA applied to the residential construction contract at issue.

The builder argued that the CPA did not apply. It argued that the CPA was at odds with the flexible nature of cost-plus construction contracts, which provided security to contractors against being left out-of-pocket for their actual costs spent on labour, materials, and subtrade accounts.[7]

The Court disagreed. The Court found that a cost-plus construction contract was not at odds with the CPA. Further, the Court found that nothing in the CPA or Construction Lien Act precluded both acts from applying to the same contract simultaneously.  The Court therefore found that the CPA can apply to cost-plus contracts concerning residential construction and renovation.[8]

The CPA applies to all “consumer transactions” if the consumer or the person engaging in the transaction with the consumer is located in Ontario when the transaction takes place. “Consumer” is defined in the CPA to mean “an individual acting for personal, family or household purposes and does not include a person who is acting for business purposes.”[9]

The Court was satisfied that the homeowners were “consumers” for the purposes of the CPA, and that the residential construction at issue was a “consumer transaction”.  As such, the Court granted summary judgment that the CPA applied to the contract in this case.[10]

Unfortunately, there was not sufficient evidence before the Court to determine whether the “budgets” in the contract constituted “estimates” under section 10 the CPA, nor whether the parties had agreed to vary any of these “estimates”. The Court therefore directed that those issues be resolved at a later trial.

Takeaways

The CPA does not apply to individuals acting for business purposes. As a result, business-to-business construction transactions will remain unaffected by this ruling.

However, this decision is very likely to impact all contractors who contract directly with homeowners (consumers) for the construction or renovation of a residence (or other similar work) in Ontario.

Contractors entering into residential construction, renovation and other similar contracts (particularly cost plus contracts) directly with consumers will now need to be careful when providing “estimates” for the cost of various items of work. If the contractor fails to obtain approval from the consumer for a change to the estimate, the builder may be precluded from charging more than 10% above the original estimate – even if the actual cost of labour and materials far exceeds the estimated price. This cannot be avoided; parties cannot contract out of the CPA.

Feel free to reach out to the authors Jeremy Rankin or Sezen Izer with any questions about this article or whether the Consumer Protection Act may apply in your case.

[1] The Fifth Wall Corp. v. Tonelli, 2022 ONSC 6590 [Fifth Wall].
[2] Fifth Wall at para 2.
[3] Fifth Wall at paras 3-5.
[4] Fifth Wall at para 4.
[5] Consumer Protection Act, 2002, S.O. 2002, c. 30, s. 10.
[6] Fifth Wall at para 7.
[7] Fifth Wall at para 19.
[8] Fifth Wall at para 23.
[9] Consumer Protection Act, 2002, S.O. 2002, c. 30, ss. 1, 2.
[10] Fifth Wall at para 28.

by Jeremy Rankin and Sezen Izer

A Cautionary Note

The foregoing provides only an overview and does not constitute legal advice. Readers are cautioned against making any decisions based on this material alone. Rather, specific legal advice should be obtained.

© McMillan LLP 2023

Insights (5 Posts)View More

Featured Insight

Buyer’s Remorse: Asset Purchaser Liable for Pre-Closing Employment Liabilities of Vendor

In a recent British Columbia decision, an asset purchaser was held liable for the pre-closing employment-related liabilities of the vendor.

Read More
Nov 29, 2024
Featured Insight

Reducing NSF Fees: Proposed Regulations Amending the Financial Consumer Protection Framework Regulations

The Governor in Council announced a proposal to amend regulations aimed at reducing non-sufficient funds (NSF) fees.

Read More
Nov 27, 2024
Featured Insight

Federal Court of Appeal Upholds Arrears Interest on Non-Existent Tax Debts: Bank of Nova Scotia v Canada, 2024 FCA 192

The Federal Court of Appeal upheld the charging of "arrears interest" on notional income tax liabilities that are completely offset by carry-backs.

Read More
Nov 27, 2024
Featured Insight

Capital Markets Tribunal Decision Confirms Legality of Hedging Transactions Despite Public Interest Concerns

The recent ruling by the Capital Markets Tribunal underscores the inherent tension between investor protection and the goals of market efficiency and fostering.

Read More
Nov 27, 2024
Featured Insight

Here We Go Again: Employers Ordered to Pay $10,000 in Moral and Punitive Damages for Improper Termination Conduct

Three recent Ontario decisions reinforce the importance of proper termination protocols due to the ever-evolving risk of moral and punitive damage awards.

Read More
Nov 27, 2024