Environmental Priorities in Insolvency Proceedings and the Impact on Lenders: Alberta Court Broadens Redwater Principles

May 24, 2023 Environmental Bulletin 4 minute read

A recent Alberta case continues the development of a line of cases at the intersection of environmental protection and bankruptcy and insolvency law in Canada. The Alberta Court of King’s Bench decision in Qualex-Landmark Towers v 12-10 Capital Corp (“Qualex”)[1] opens the door for private citizens to try to establish a “super priority” over registered mortgagees where environmental remediation obligations are at issue. The decision has important implications for financial institutions and other lenders who loan against the value of real property.

The Qualex decision relies and builds on the Supreme Court of Canada’s (“SCC”) landmark decision in Orphan Well Association v. Grant Thornton Ltd. (“Redwater”).[2]

A Review of Redwater

In Redwater, the SCC considered how environmental remediation obligations should be prioritized in bankruptcy. Pursuant to Alberta’s regulatory regime, a company is required to obtain a license in order to extract oil and gas resources.[3] Specific environmental obligations are imposed on license holders, including end-of-life obligations to ensure the environmental security of a well.[4] Such obligations may persist through and after insolvency proceedings pursuant to Alberta statutes, such as the Oil and Gas Conservation Act,[5] the Pipeline Act,[6] and the Environmental Protection and Enhancement Act.[7]

The principal issue in Redwater was that the associated costs of the insolvent company’s end-of-life obligations with respect to its abandoned oil wells would exceed its asset sale proceeds in the insolvency proceeding.[8] The company’s receiver and trustee posited that these remediation obligations conflicted with the provisions of the Bankruptcy and Insolvency Act (the “BIA”),[9] particularly section 14.06,[10] but the SCC concluded otherwise.[11]

The Court then applied the test set out in AbitibiBowater Inc., Re[12] to determine whether the environmental claims at issue were provable in bankruptcy and ultimately concluded that the company’s environmental remediation obligations did not conflict with the BIA’s priority scheme.

In issuing the decision in Redwater, the SCC signaled a trend toward heightened environmental responsibility of debtors and their receivers and trustees as well as the creation of a “super priority” for certain environmental obligations. A more detailed discussion of the Redwater decision and its implications can be found in our earlier bulletins here and here.

Earlier Applications of Redwater in Alberta

Two recent decisions that build on and consider Redwater are the Alberta Court of Appeal’s 2022 decision in Manitok Energy Inc (Re) (“Manitok”)[13] and the Alberta Court of King’s Bench decision in Orphan Well Association v. Trident Exploration Corp. (“Trident”).[14]

In Manitok, the receiver was tasked with determining priority between two builders’ liens and the oil and gas well abandonment and reclamation obligations of the insolvent company.[15] The Court applied Redwater, finding that the assets in the estate should have been made available to discharge the abandonment and reclamation obligations regardless of the fact that the assets were sold by the trustee and converted to cash.[16]

Similarly, the Alberta Court of King’s Bench, relying on Redwater and Manitok, determined in Trident that the application of the now established super priority principles required that the abandoned oil and gas well reclamation obligations be given precedence over municipal tax obligations.[17]

Application of Redwater to Private Interests

The reasoning in Qualex potentially broadens the reach of super priority principles. In that case, 12-10 Capital Corp (“Capital Corp”) owned contaminated real property (the “12-10 Lands”). This contamination had migrated onto and impacted the adjacent property owned by Qualex-Landmark Towers Inc. (“QLT”)[18] and Alberta Environment and Parks (“AEP”) had directed Capital Corp to complete an environmental remediation plan to address it.[19] Upon discovery of Capital Corp’s insolvency (despite not yet subject to insolvency proceedings) and its intention to sell the 12-10 Lands, QLT brought a claim against Capital Corp seeking an order requiring Capital Corp to complete the remediation as directed by AEP and a finding that Capital Corp’s environmental obligations took priority over its outstanding mortgages. Given that there would be insufficient net proceeds from the sale of the 12-10 Lands to complete the environmental obligations after the mortgages were re-paid, QLT sought an attachment order to hold any sale proceeds of the 12-10 Lands in trust for the purpose of the environmental remediation work pending the outcome of its claim. [20]

In keeping with Redwater, Manitok and Trident and in line with the polluter pays principle, the Court recognized that it would be inappropriate to permit an insolvent corporation that caused or was responsible for the contamination at issue to escape environmental remediation obligations while simultaneously paying its secured lenders.[21] The Court held that, subject to hearing full argument on the matter at trial, a super priority could apply against Capital Corp with QLT as a likely beneficiary.

Of note to lenders, the super priority would displace the priority that would otherwise be held by the mortgagees.

The Court also confirmed that QLT was not required to be a “regulator” for the purposes of benefitting from a super-priority claim, stating that regardless of if an acting body is a “regulator” or not, a polluter is vested with an obligation to remediate.[22]

Qualex and Future Implications

This line of case law emphasizes the need for prospective lenders to exercise thorough due diligence with respect to any real property involved in financing transactions. As environmental issues may remain hidden for years and often their complete scope is not fully known at the time of a transaction, such due diligence may identify previously unknown environmental conditions, risks and obligations associated with the property. This information will assist a lender in making an informed decision based on the possibility of such environmental obligations being granted priority over the secured assets in the event of an insolvency proceeding or civil dispute.

[1] Qualex-Landmark Towers Inc v 12-10 Capital Corp, 2023 ABKB 109 [Qualex].
[2] Orphan Well Association v Grant Thornton Ltd, 2019 SCC 5 [Redwater].
[3] Ibid at para 12.
[4] Ibid at paras 16 – 17.
[5] Oil and Gas Conservation Act, RSA 2000, c O-6.
[6] Pipeline Act, RSA 2000, c P-15.
[7] Environmental Protection and Enhancement Act, RSA 2000, c E-12.
[8] Redwater, supra note 2 at para 50.
[9] Bankruptcy and Insolvency Act, RSA 1985, c B-3.
[10] Redwater, supra note 2 at para 53.
[11] Ibid at para 114.
[12] AbitibiBowater Inc, Re, 2012 SCC 67.
[13] Manitok Energy Inc (Re), 2022 ABCA 117 [Manitok].
[14] Orphan Well Association v Trident Exploration Corp, 2022 ABKB 839 [Trident].
[15] Manitok, supra note 13 at para 2.
[16] Ibid at paras 30, 32.
[17] Trident, supra note 14 at para 17.
[18] Qualex, supra note 1 at para 12.
[19] Ibid at para 16.
[20] Ibid at para 8.
[21] Ibid at paras 87-88.
[22] Ibid at para 94.

by Talia Gordner, Adam Maerov and Ryan Johnson (Articling Student)

A Cautionary Note

The foregoing provides only an overview and does not constitute legal advice. Readers are cautioned against making any decisions based on this material alone. Rather, specific legal advice should be obtained.

© McMillan LLP 2023

Insights (5 Posts)View More

Featured Insight

Budget 2024: Legislative Changes of Note for Investment Funds

In Budget 2024, the Government acknowledges that the restrictions placed on the property that may be held by registered plans have become unduly complex.

Read More
Apr 19, 2024
Featured Insight

Budget 2024: Clean Energy Incentives and Resource Sector Measures

Budget 2024 prioritizes Canada’s transition to a net-zero economy and contains several measures aimed at facilitating that ongoing transition.

Read More
Apr 19, 2024
Featured Insight

Budget 2024: Synthetic Equity Arrangement Restrictions Tightened

Budget 2024 proposes to tighten the “synthetic equity arrangement” anti-avoidance rule by eliminating the no “tax-indifferent investor” exception.

Read More
Apr 19, 2024
Featured Insight

Budget 2024: Increases in the Taxation of Capital Gains

Budget 2024 proposes to significantly change how capital gains are taxed under the Income Tax Act (Canada).

Read More
Apr 19, 2024
Featured Insight

Budget 2024: Expanded Relief for Non-Resident Service Providers

Budget 2024 will expand the circumstances under which relief may be granted from withholdings on payments made to non-residents that render services in Canada.

Read More
Apr 19, 2024